Annotated Study Enclosures

This is a complete list of all enclosures for a given community. If different communities are involved make sure that you are only listing the enclosures for the community whose determination you are working on (for instance, if the revision impacts two counties, don't list all the enclosures that have been prepared, just the ones for this determination). List table numbers and profile panel numbers in the notes section.

Ordinance Adoption

Select "Yes" if the revision shows new BFEs or floodway boundaries, and the community being revised has not adopted a high enough level of regulation into their floodplain management ordinances. This will require the community to adopt the minimum level of regulation within 6 months, in order for the LOMR to become effective.

Legal Paragraphs

19A: Physical map revision will not follow and no other map update activities are in progress
We will not physically revise and republish the FIRM and FIS report for your community to reflect the modifications made by this LOMR at this time. When changes to the previously cited FIRM panel(s) and FIS report warrant physical revision and republication in the future, we will incorporate the modifications made by this LOMR at that time.
19B: When physical map revision will follow (two paragraphs)
We will physically revise and republish the previously cited FIRM panel(s) and the FIS report to reflect the modifications made by this LOMR, and issue Preliminary copies for community review. So that we may provide your community with the most up-to-date information possible, we request that your community review the effective FIRM panel(s) referenced above and the effective FIS report to determine if any additional changes are warranted. Examples of possible changes include updates to corporate limits, new streets within or adjacent to designated SFHAs, and revised floodway boundary delineations.
To assist us in processing the revised FIRM and FIS report in a timely manner, we request that your community submit changes within 30 days of the date of this letter. We will review all information received during this 30 day period and incorporate it, as appropriate, into the Preliminary copies of the revised FIRM and FIS report. The Preliminary copies are scheduled to be delivered for review in approximately ___ months.
19C: When physical map revision is ongoing
Based on new detailed flood hazard information for the subject community, we plan to physically revise and republish the previously cited FIRM panel(s) and the FIS report for your community. We will incorporate the modifications made by this LOMR into the revised map panel(s) and FIS report before we issue Preliminary copies for review by your community. The Preliminary copies are scheduled to be delivered for review in approximately ___ months.
19D: When RFIS is ongoing
The modifications made by this LOMR are based on data used to prepare the effective FIRM. We are reviewing a detailed analysis for dynamic floodsomness for the project. When the results of the new analysis are incorporated and the revised FIRM [and FIS report] become(s) effective, the new FIRM will supersede this LOMR. If appropriate, the new map panel(s) and FIS report will reflect the modifications made by this LOMR.
19E: When Effective FBFM is not being revised because floodway is not affected by revision
Because this revision does not involve floodway changes, we are not revising the Flood Boundary and Floodway Map (FBFM); therefore, no annotated copies of the FBFM are enclosed. Unless a subsequent physical map revision involves floodway changes for the FBFM panel(s), we will not revise the FBFM to show the modifications described in this LOMR.
19F: When preparation of Preliminary DFIRM or other new countywide map is ongoing
We are preparing a revised FIRM and FIS report for ___ County in our countywide format; therefore, we will not physically revise and republish the FIRM and FIS report for your community to incorporate the modifications made by this LOMR at this time. Preliminary copies of the countywide FIRM and FIS report, which will present information from the effective FIRMs and FIS reports for your community and [other] incorporated communities in ___ County, will be distributed for review in approximately months. We will incorporate the modifications made by this LOMR into the Preliminary countywide FIRM before it is distributed, and the modifications will be included when the countywide FIRM becomes effective.
19G: When Preliminary DFIRM or other new countywide map has been submitted to community for review
We are processing a revised FIRM and FIS report for ___ County in our countywide format; therefore, we will not physically revise and republish the FIRM and FIS report for your community to incorporate the modifications made by this LOMR at this time. Preliminary copies of the countywide FIRM and FIS report, which present information from the effective FIRMs and FIS reports for your community and [other] incorporated communities in ___ County, were submitted to your community for review on ___. We will incorporate the modifications made by this LOMR into the countywide FIRM and FIS report before they become effective.
19H: When results of LOMR will not be included in an ongoing update to the FIRM, and will be superseded when the FIRM becomes effective
We are processing a revised FIRM and FIS report for your community, which will become effective on ___. Because the effective date has already been established, we will not incorporate the modifications made by this LOMR into the revised FIRM and FIS report before they become effective. Therefore, the modifications made by this LOMR will be superseded when the revised maps and FIS report become effective. After the effective date, we will issue a letter to revalidate the modifications made by this LOMR and revise the newly effective FIRM and FIS report.
19I: When results of LOMR will not be included in a new countywide FIRM and FIS report, and will be superseded when the FIRM and FIS report become effective
We are processing a FIRM and FIS report for ___ County, ___, and its incorporated areas in our countywide format. The countywide FIRM and FIS report, which include flood hazard information for your community, will become effective on ___. Because the effective date has already been established, we will not incorporate the modifications made by this LOMR into the countywide FIRM and FIS report before they become effective. Therefore, the modifications made by this LOMR will be superseded when the countywide FIRM and FIS report become effective. After the effective date, we will issue a letter to revalidate the modifications made by this LOMR and revise the newly effective FIRM and FIS report.