Frequently Asked Questions: MIP Workflow – Amendments

Question


What do I do if the required fee amount is incorrect?

Answer


If the case has not passed 'Process Request' the analyst/engineer can update this field at the 'ReviewDataReceived' or 'Process Request' activity.

For Amendment – If the project is at A14 (Review Draft Determination), Amendment Project Lead can reject the project to move it back to A05 (Process Request) where the Amendment Task Lead can make the change.

For Revision – If the project is at R08 (Review Determination), FEMA Revision Lead can reject the project to move it back to R05 (Process Request) where the Revision Task Lead can make the change.

Return to FAQ Page