Frequently Asked Questions: MIP Workflow – Amendments

Question


'Assign Project Resource' has already been completed. Why hasn't 'ReviewDataReceived' started?

Answer


For 'Not Exempt' fee type project. As soon as Assign Project Resources is completed, the Review Data Received (A03) activity is spawned. If A03 activity is completed before Administer Fee (A13) activity, the system will automatically complete A13 activity. If there is an outstanding balance, a new A16 (Receive Additional Fee) activity is spawned.

To determine the current activity available for a project, you can view the 'Project Workflow Information' under the LOMC Case Tracking report.

Return to FAQ Page